Asbestos surveys and ACP-5 filing in New York City

Before DOB issues most work permits, a NYC DEP-certified Asbestos Investigator must look at what the work will disturb. We survey, sample, and file the ACP-5 when your scope qualifies.

15 RCNY Chapter 1NYS ICR 56 (12 NYCRR 56)40 CFR 61 Subpart MNYC DOB permits
HA-03 · BULK SAMPLEPipe insulation, 6 in.PLM · friable HA-07 · BULK SAMPLEFloor tile 9×9 + masticNOB · PLM then TEM
Bulk samples are located, photographed and logged for the report.

What we do

Survey, sample, report, file

  • Pre-renovation and pre-demolition surveysInspection of every material the scope of work will touch: pipe and boiler insulation, flooring, plaster, roofing, caulks and more.
  • ACP-5 Asbestos Assessment ReportsPrepared and filed with NYC DEP when no asbestos-containing material will be disturbed, or only a minor-project quantity.
  • Bulk sampling and laboratory analysisSamples go to NYS ELAP-accredited labs. Non-friable organically bound materials such as floor tile get PLM and, when needed, TEM.
  • Survey reports for abatement planningWhen ACM must come out, our survey tells the owner and the contractor exactly where it is and how much there is.
  • Asbestos air samplingAir sampling by an independent consultant to give building occupants reassurance about air quality.

Requirements

Who needs an asbestos survey

NYC rule
NYC DEP's asbestos rules (15 RCNY Chapter 1) require an asbestos investigation by a DEP-certified Asbestos Investigator before DOB issues permits for most renovation, alteration and demolition work.
ACP-5
The Asbestos Assessment Report the investigator files when the work will disturb no ACM, or no more than a minor-project amount. DOB checks it with the permit application.
New York State
Industrial Code Rule 56 requires an asbestos survey before demolition, renovation, remodeling or repair of buildings built before January 1, 1974.
Federal
EPA NESHAP (40 CFR 61 Subpart M) requires a thorough inspection before demolition or renovation of regulated facilities.
Definition
Asbestos-containing material (ACM) is any material containing more than 1% asbestos.

NYC asbestos project size categories

Surface materials (square feet)
Minor10 sq ft or less
Smallmore than 10, under 160
Large160 sq ft or more
Pipe and linear materials (linear feet)
Minor25 ln ft or less
Smallmore than 25, under 260
Large260 ln ft or more
Size categories under 15 RCNY Chapter 1. Segments show categories, not proportional quantities. A minor project may still proceed with an ACP-5; small and large projects require licensed abatement with DEP notification.

Where the ACP-5 fits

You plan work that needs a DOB permitrenovation, alteration, plumbing, demolition
↓
Asbestos surveyNYC DEP-certified Asbestos Investigator · bulk samples to ELAP lab
↓ results
No ACM disturbed, or minor project onlyThe investigator files the ACP-5 Asbestos Assessment Report with DEP → submit to DOB with permit
ACM disturbed above minor quantitiesAbatement by a licensed contractor, filed with DEP before work begins.

Process

How an asbestos survey runs

  1. Scope review

    Send drawings or a written scope. We match the survey to the areas and materials the work will disturb.

  2. Inspection

    Visual inspection and bulk sampling of each homogeneous material, with sample locations photographed and logged.

  3. Lab analysis

    PLM at an ELAP-accredited lab; non-friable organically bound samples go to TEM when PLM is inconclusive or negative.

  4. Report and ACP-5

    Signed survey report with quantities and locations. If the project qualifies, we file the ACP-5 with DEP.

FAQ

Common questions

What is the difference between an ACP-5 and an ACP-7?

The ACP-5 is filed by the asbestos investigator to document that a project will not disturb ACM above minor quantities. The ACP-7 is the asbestos project notification filed by the licensed abatement contractor when abatement is needed.

Why are floor tiles analyzed twice?

Floor tile, mastic and roofing are non-friable organically bound (NOB) materials. Polarized light microscopy can miss asbestos in them, so New York requires TEM confirmation before a NOB sample can be called negative.

How fast can I get an ACP-5?

Turnaround depends on the size of the survey and lab timing. Tell us your filing date when you request a quote and we will schedule around it.

Next step

Filing for a DOB permit?

Send the address and your scope of work. We will confirm whether an ACP-5 is possible and quote the survey.